WhatsApp
JJMac Melton Road Hull – Site Remediation

Melton Road Hull

Site Remediation

JJM 3037 – Storage Yards – Remediation and Stabilisation
Project JJM 3037 – Storage Yards – Remediation and Stabilisation
Location Melton Road North Ferriby Hull
Client RIX Group
Key works delivered RDC Rapid Dynamic Compaction and Capping Stabilisation
Project Duration 6 weeks
Stabilised Area 40,000m2 RDC and Stabilisation
Earthworks By JJMac Ltd
PROJECT OVERVIEW
PROJECT CHALLENGES
ENGINEERING AND SOLUTIONS TO OVERCOME THE CHALLENGES
REMEDIATION and STABILISATION WORKS
JJMac operate a fleet of very agile equipment.
Tractor mounted Wirtgen 250WS Mixers were selected for this project due to the challenging site conditions earlier on in the project.
Our Dustless Stehr was also utilised for all works near the existing offices during any windy
conditions which enabled us to progress works in all conditions.
Melton Road Hull Storage Yards – Remediation and Stabilisation 2
REMEDIATION and STABILISATION WORKS
JJMac carried out Topographical Surveys of the site and created a Finished Level Model for the GPS Dozer Melton Road Hull Storage Yards – Remediation and Stabilisation 3 RDC Rapid Dynamic Compaction was carried out on the Land Fill Site prior to stabilisation of the Capping layer. The RDC will ensure sufficient compaction in the upper 2.0m of existing fill.

This particular 16tn RDC roller will influence approx 6.0m deep 300mm layers for cement stabilsiation.
Melton Road Hull Storage Yards – Remediation and Stabilisation 4
EXCAVATIONS AND REMOVAL OF OBSTICLES
Sitewide excavations to approx. 600mm deep was undertaken to ensure a clean separation capping is provided between the landfill and finished levels
Screening and Crushing of made ground material was carried out prior to being replaced in 300mm layers for cement stabilsiation.
Melton Road Hull Storage Yards – Remediation and Stabilisation 5 Melton Road Hull Storage Yards – Remediation and Stabilisation 8
Melton Road Hull Storage Yards – Remediation and Stabilisation 6
Melton Road Hull Storage Yards – Remediation and Stabilisation 7
STABILISATION WORKS
Stabilisation was undertaken using Tractor Mounted Wirtgen WS320. Daily productivity by the stabilisation crew approx. 4,000m2 per day Melton Road Hull Storage Yards – Remediation and Stabilisation 9
COMPLETED WORKS
Stabilisation Layers completed Melton Road Hull Storage Yards – Remediation and Stabilisation 10 Type1 Capping to stabilised material Melton Road Hull Storage Yards – Remediation and Stabilisation 11
ADVANTAGES
The Cement Stabilisation works had numerous advantages to this site.
BENEFITS TO CLIENT

Cost Saving
75%
Programme Reduction
60%
Vehicle Movements Reduction
80%
Imported Aggregate Reduction
100%
Material Sent To Landfill Reduced By
100%
Stone Layer Depth Reduction
50%


SOIL STABILISATION RDC REMEDIATION GROUND STABILISATION EARTHWORKS