JJMac Marina Dock Yards – Remediation and Stabilisation

Marina Dock Barrow

Site Remediation

JJM2975 – Dock Yards – Remediation and Stabilisation
Project JJM2975 – Dock Yards – Remediation and Stabilisation
Location Marina Dock Barrow in Furness
Client Barrow Borough Council
Key works delivered Excavations, screening and crushing and Stabilisation
Project Duration June 23 – Nov 23
Stabilised Area 110,000m3 modified and 240,000m2 stabilised
Earthworks By JJMac Ltd
Marina Dock Barrow Map
PROJECT OVERVIEW
Dock Yards – Remediation and Stabilisation
PROJECT CHALLENGES
ENGINEERING AND SOLUTIONS TO OVERCOME THE CHALLENGES
To overcome the project challenges set by the client, our team:
REMEDIATION and STABILISATION WORKS
JJMac operate a fleet of very agile equipment.
Tractor mounted Wirtgen 250WS Mixers were selected for this project due to the challenging site conditions earlier on in the project.
Our Dustless Stehr was also utilised for all works near the existing offices during any windy
conditions which enabled us to progress works in all conditions.
Dock Yards – Remediation and Stabilisation 1
EXCAVATIONS for SCREENING and CRUSHING
Sitewide excavations to approx. 2.0m deep was undertaken in sections and phases to
minimise material movement and stockpiling
Screening and Crushing of made ground material was carried out prior to being replaced in
300mm layers for cement stabilsiation.
Dock Yards – Remediation and Stabilisation 3
Dock Yards – Remediation and Stabilisation 4
STABILISATION WORKS
Stabilisation was undertaken Dock Yards – Remediation and Stabilisation 5
COMPLETED WORKS
Dock Yards – Remediation and Stabilisation 6 Dock Yards – Remediation and Stabilisation 7
ADVANTAGES
The Cement Stabilisation works had numerous advantages to this site.
BENEFITS TO CLIENT

Cost Saving
50%
Programme Reduction
40%
Vehicle Movements Reduction
75%
Imported Aggregate Reduction
80%
Material Sent To Landfill Reduced By
100%
Stone Layer Depth Reduction
70%


SOIL STABILISATION RDC REMEDIATION GROUND STABILISATION EARTHWORKS