JJMac Hobhole Lane Boston – Road Restoration

HobHole Pumping Station Road Restoration

Hobhole Lane Boston

Hobhole – Boston PE22 0RB
Project JJMac 2639 – Hobhole
Location Hobhole Lane Boston
Client IDB Internal Drainage Board
Key works delivered Road Crushing, Stabilisation and Surfacing
Project Duration Dec 2021 - 2 weeks
Stabilised Area 6000 m2
Earthworks By JJMac
Internal Drainage Board – HobHole Pumping Station Road Restoration JJMac Hobhole Boston
PROJECT OVERVIEW
Public Highways Access Road to IDB Hobhole Pumping Station had deteriorated and becoming dangerous for delivery truck and the like due to subsidence to one side. The shoulders of the road needed to be reinforced before any surfacing could be done. Simply overlaying and filling the depressed area was not an option as previously done.
JJMac offered a solution to in-situ stabilise the shoulders and to recycle the existing road material.

JJMac Hobhole Boston 2 JJMac Hobhole Boston 3
PROJECT CHALLENGES
Our team were challenged with designing a stabilised subbase for the road shoulders.
ENGINEERING AND SOLUTIONS TO OVERCOME THE CHALLENGES
To overcome the project challenges, set by the client, our team:

STABILISATION WORKS IN PROGRESS
Once the areas for stabilisation were identified and marked out, JJMac site team set to work Crushing the surface 150mm and preparing the existing road material into a uniform recycled material for stabilisation.
JJMac Hobhole Boston 4 JJMac Hobhole Boston 5
We then mixed and stabilised 350mm to enhance the shoulders of the road and create a new Non-Frost Susceptible Stabilised Foundation>30% CBR on the complete roadway. Roadway Trimmed level and ready for Stabilsiation and Stabilised Roadway ready for Surfacing JJMac Hobhole Boston 6 JJMac Hobhole Boston 7
The GGBS and Lime Combination was allowed 72 hours to cure without any heavy traffic. Residents cars were fine to travel on the stabilised material as they needed access.
COMPLETED WORKS
JJMac Hobhole Boston 8 JJMac Hobhole Boston 9
BENEFITS TO CLIENT
JJMac were able to offer a Design and Stabilise package for the reconstruction and shoulder stabilisation on this section of the access road. All existing material recycled and utilised with Lime and GGBS to reduce further the Carbon footprint of the works.


Cost Saving
60%
Programme Reduction
75%
Vehicle Movements Reduction
80%
Imported Aggregate Reduction
75%
Material Sent To Landfill Reduced By
100%
Stone Layer Depth Reduction
70%


Thanks to all involved, the roads and tracks look great. Top job.

Ed Johnson
Chief Engineer, Internal Drainage Board


SOIL STABILISATION RDC REMEDIATION GROUND STABILISATION EARTHWORKS