Boston

STORAGE DEPOT

JJM2643 - Transport Depot
Project JJM2643 - Transport Depot
Location Boston PE20 3AN
Client Turner Transport
Key works delivered Ground Stabilisation
Project Duration Sept 2021 - 4 WEEKS
Stabilised Area 8000 m2
Boston 1
PROJECT OVERVIEW
Turners Transport at Boston operates approx. 200 lorries from this depot.
The depot was an old yard that expanded quickly. The main problem on the depot was poor drainage and poor very poor surface condition of the yard make up.
Ongoing problems for logistics and trying to store lorries out of the flooded areas and large potholes causing damage to the lorries and trailers
PROJECT CHALLENGES
Our team were challenged to restore the surface of the yard and provide a safe operating area for the lorry drivers and all staff in the depot. Levels were not great on the yard with falls in the wrong direction. There was no drainage system in the yard to work with.
ENGINEERING AND SOLUTIONS TO OVERCOME THE CHALLENGES
To overcome the project challenges set by the client, our team:


BENEFITS TO CLIENT
JJMac Ground Stabilisation were able to offer a turnkey package to our client on this project. We could carry out initial Surveys and Assessments of the yard and from this information, we could work with out client to advise on a Drainage Solution and a Restoration Solution for the yard surface. Boston 7


Cost Saving
50%
Programme Reduction
45%
Vehicle Movements Reduction
80%
Imported Aggregate Reduction
80%
Material Sent To Landfill Reduced By
100%
Stone Layer Depth Reduction
50%


SOIL STABILISATION RDC REMEDIATION GROUND STABILISATION EARTHWORKS