JJMac Ansty Park Coventry – Building and Externals Stabilisation

Ansty Park Coventry

Building and Externals Stabilisation

JJM2973 – Building and Storage Depot Stabilisation
Project JJM2973 – Building and Storage Depot Stabilisation
Location Prospero – Ansty Park Development
Client McLarens
Key works delivered Bulk Fill Modification, Capping and Subbase Replacement stabilisation
Project Duration March 23 – Sept 23
Stabilised Area 110,000m3 modified and 240,000m2 stabilised
Earthworks By Heywood HCD
Ansty Park Coventry
PROJECT OVERVIEW
PROJECT CHALLENGES
ENGINEERING AND SOLUTIONS TO OVERCOME THE CHALLENGES



MODIFICATION AND STABILISATION WORKS
JJMac operate a fleet of very agile equipment.
Tractor mounted Wirtgen 250WS Mixers were selected for this project due to the challenging site conditions earlier on in the project.
Our Dustless Stehr was also utilised for all works near the existing offices during any windy conditions which enabled us to progress works in all conditions.
Ansty Park Coventry 1


LIME MODIFICATION TO BULK FILL MATERIAL
Bulk Fill Modification was undertaken using 1% Lime to condition the material for optimum compaction to achieve >5% CBR Ansty Park Coventry 2 Ansty Park Coventry 3


RDC Rolling Dynamic Compaction to Bulk Fill Material
We also utilised RDC Rolling Dynamic Compaction on the bulk fill which also achieved >5% on some of the soils that had a natural moisture content close to the range for optimum compaction. Ansty Park Coventry 2 Ansty Park Coventry 4


Stabilisation works to Building footprint
Stabilisation was undertaken for the Building Footprint using 1% Lime and 3% Cement to achieve >30% CBR Ansty Park Coventry 5 Water addition as necessary to ensure the Moisture Content Value MCV was within range at all times Ansty Park Coventry 6 All works were tested during the construction process for MCV and CBR


Completed Works
Stabilised areas under building footprints had min 100mm 6f material placed to protect the stabilised material

Foundations were dug and poured directly into the excavations without the need for any formwork. The stabilised material was solid all the way through the Bulk Fill. Ansty Park Coventry 7 30% CBR stabilised ground below the buildings Ansty Park Coventry 8


ADVANTAGES
The works had numerous advantages to this site.


BENEFITS TO CLIENT
Cost Saving
50%
Programme Reduction
40%
Vehicle Movements Reduction
75%
Imported Aggregate Reduction
80%
Material Sent To Landfill Reduced By
100%
Stone Layer Depth Reduction
70%


SOIL STABILISATION RDC REMEDIATION GROUND STABILISATION EARTHWORKS