NEW LIDL STORE

Stowmarket

Stowmarket – New Store
Project JJM2529 – Stockpile Material Treatment
Location Stowmarket
Client Lidl
Key works delivered Drying and Stockpile Material Treatment – Lime and Cement Mixing
Project Duration Jan 2021 - 4 weeks
Stabilised Area 5000 m2
Earthworks By Client
Stowmarket 1 Stowmarket 2
PROJECT OVERVIEW
Site had become water-logged and very badly cut up from drainage and other groundworks. JJMac invited to site to offer solutions to enable works to progress and to treat the saturated site and return to a workable site.
PROJECT CHALLENGES
Our team were challenged by the levels site and water ingress from nearby water sources such as a river alongside the site and poorly backfilled ponds at time of remediation. Jan/Feb 21 also very wet and snow on site
ENGINEERING AND SOLUTIONS TO OVERCOME THE CHALLENGES
To overcome the project challenges set by the client, our team:
Lime Drying and Cement Mixing
Stowmarket Lime Drying Stowmarket Cement Mixing
Stockpile material Placed and Cement Mixed in Layers
Stowmarket Stockpile material Placed and Cement Mixed in Layers


ADVANTAGES
The works had a two-fold advantage to this site.
BENEFITS TO CLIENT
Cost Saving
60%
Programme Reduction
75%
Vehicle Movements Reduction
80%
Imported Aggregate Reduction
66%
Material Sent To Landfill Reduced By
100%
Stone Layer Depth Reduction
80%


SOIL STABILISATION RDC REMEDIATION GROUND STABILISATION EARTHWORKS