JJMac Long Stratton Bypass – Compound and Haul Road Stabilisation

Long Stratton Bypass

Compound and Haul Road Stabilisation

JJM3015 – Temporary Works Compound Stabilisation
Project JJM3015 – Temporary Works Compound Stabilisation
Location Long Stratton – Long Stratton Bypass
Client Octavious
Key works delivered Earthworks including Topsoil Strip, levelling and Capping Stabilisation
Project Duration 4 Weeks
Stabilised Area 20 000 m2
Earthworks By JJMac
Long Stratton Bypass Map
PROJECT OVERVIEW
PROJECT CHALLENGES
ENGINEERING AND SOLUTIONS TO OVERCOME THE CHALLENGES
To overcome the project challenges set by the client, our team:
MODIFICATION AND STABILISATION WORKS
JJMac operate a fleet of very agile equipment.
Tractor mounted Wirtgen 250WS Mixers were selected for this project due to the challenging site conditions earlier on in the project.
Our Dustless Stehr was also utilised for all works near the existing offices during any windy conditions which enabled us to progress works in all conditions.
Long Stratton Bypass 1
EARTHWORKS AND STABILISATION WORKS
Capping Layer stabilisation to min 30% using 3.5% by Vol CEMI Long Stratton Bypass 2 Long Stratton Bypass 3
ADVANTAGES
The works had numerous advantages to this site.
BENEFITS TO CLIENT
JMac are experts in Soil and Ground Stabilisation using lime, cement and other binder materials. Ground Stabilisation geotechnically enhances waterlogged or weaker soils and allows for greater weight bearing for construction materials. JJMac can provide an exceptionally cost-effective construction method for improving the weight bearing properties of any soil found on site and at a competitive rate.


Cost Saving
50%
Programme Reduction
40%
Vehicle Movements Reduction
75%
Imported Aggregate Reduction
80%
Material Sent To Landfill Reduced By
100%
Stone Layer Depth Reduction
70%