JJMac VIKING LINK – CONTRACTORS COMPOUND

Treating Stockpile

VIKING LINK – CONTRACTORS COMPOUND

JJM2643 – Contractors Compound
Project JJM2643 – Contractors Compound
Location Bicker Fen Lincs
Client Siemens / National Grid
Key works delivered Treating Stockpile of 6E material to create 9A material Contractors Compound
Project Duration Nov 2021 - 2 weeks
Stabilised Area 4000 m2
Earthworks By JJMac Limited
PROJECT OVERVIEW
PROJECT CHALLENGES
The project had challenges to overcome as the material required a separation membrane to be placed at formation. This ruled out In-Situ mixing of the 6E material.
The 6E material had to be lifted and riddled to remove any fabric and terram etc. The lifted and riddled material was mixed with the cement binder ex-situ and placed on the new Terram, trimmed and Compacted
Stockpile material being raked Bricker 1
ENGINEERING AND SOLUTIONS TO OVERCOME THE CHALLENGES
To overcome the project challenges set by the client, our team:


EARTHWORKS AND STABILISATION DURING CONSTRUCTION PHASE
Mixing and placing of Stabilised Material in flow Bricker 2 Bricker 3 All Earthworks and Screening of material was carried out by JJMac working with Siemens and the land owners to ensure that all Bio Diversity measures were adhered to at all times. Bricker 4
ADVANTAGES
The works had numerous advantages to this site.
BENEFITS TO CLIENT
Cost Saving
60%
Programme Reduction
30%
Vehicle Movements Reduction
90%
Imported Aggregate Reduction
95%
Material Sent To Landfill Reduced By
100%
Stone Layer Depth Reduction
25%


SOIL STABILISATION RDC REMEDIATION GROUND STABILISATION EARTHWORKS